Simulators

Breaker Testing

480V Breaker - Primary Injection

Practice a detailed 480V breaker primary-injection sequence after the real-world LOTO/live-dead-live hold point: settings documentation, per-phase long-time, short-time, instantaneous, and ground-fault pickup/trip checks.

Objective 1/22Score 100%Guided

Record trip unit settings and close for current path

After the real-world LOTO and live-dead-live safety hold point is complete, select the primary injection set, record as-found settings, close the breaker in the test position, set cooldown ready, and choose through-pole return.

Current Objective

Record trip unit settings and close for current path

A tech photographs the trip unit, writes the sensor/rating plug, confirms the mechanical trip path, verifies de-energized condition per site procedure, then closes the breaker to create a current path.

Why

Pickup and trip results only mean something when compared to the trip unit settings and the approved coordination study. Live-dead-live is still required in the field, but it is not scored as a simulator test step here.

Safety

High-current leads can jump, heat, or arc if poorly clamped. Keep people clear and use the test set interlocks.

Tip

Give thermal memory and the test set time to recover between long-time shots so one test does not contaminate the next.

Safety Hold Point

This simulator starts after the real-world LOTO and live-dead-live check. In the field, use the properly rated tester, prove it on a proving unit or known live source, test for absence of voltage, then prove it again before installing test leads.

Loadout

Test Bench

Setup Required

Required Now

Test Set

Required

Breaker State

Required

Trip Unit Settings

Required

Function Selector

Return Path

Required

Cooldown / Memory

Required

Sim Workbench

Lead Placement

Select a lead, then hit the highlighted target nodes.

Expected for Current Step

Current output 1: A line terminal. Current output 2 / return: A load terminal. Lead order is flexible for this check.

Animated Breaker

Route the two high-current leads through the pole or ground-return path for the selected function.

Primary Injection

High-current test set

Current output 1 and 2 feed one pole at a time.

A
B
C

Breaker poles

Ground fault

Current output 1

Not placed

Current output 2 / return

Not placed

Step Checklist

Record trip unit settings and close for current path
A-phase Long-time pickup
A-phase Long-time trip
A-phase Short-time pickup
A-phase Short-time trip
A-phase Instantaneous trip
A-phase Ground pickup
A-phase Ground trip
B-phase Long-time pickup
B-phase Long-time trip
B-phase Short-time pickup
B-phase Short-time trip
B-phase Instantaneous trip
B-phase Ground pickup
B-phase Ground trip
C-phase Long-time pickup
C-phase Long-time trip
C-phase Short-time pickup
C-phase Short-time trip
C-phase Instantaneous trip
C-phase Ground pickup
C-phase Ground trip

Field Intel

Understand that primary injection proves the breaker, sensors, trip unit, and mechanical trip path together.

Separate pickup tests from trip-time tests so settings and curves can be explained clearly.

Run each phase deliberately instead of assuming one good pole proves the whole breaker.

Use the correct return path for ground-fault testing instead of treating it like a normal phase shot.

Document cooldown, thermal memory, settings, and resets because they change what the readings mean.

Mistakes Tracked

No mistakes yet. Good simulator runs come from correct setup, lead placement, and sequence discipline.

Readings

Correct the setup, place leads, and run the current step to generate simulated readings.

Profile History

No saved attempts yet. Completed reports show up here and on the simulator landing page.

Final Report